Following a 2016 fire that severely damaged multiple structures at the former Risdon manufacturing site, the Waterbury Development Corporation (WDC) led a full demolition and cleanup effort. In 2018, all remaining buildings were demolished down to the concrete slabs and debris was removed for off-site disposal, clearing the way for future redevelopment of the property.
Location: Waterbury, CT (Former Risdon Site)
Status: Completed (2018)
Key Partner: Manafort Brothers – Demolition Contractor
Highlights:
• Fire-damaged industrial buildings demolished
• Full debris removal and off-site disposal
• Site cleared to slab for future redevelopment opportunities
• Addressed safety hazards and blight on the property