698 South Main Street-Anamet Project Phase II
Anamet Phase II of three buildings-Finished Phase II Completed: Demolition of three remaining buildings and smokestack Highbay Building abated. Removal of PCB Windows Phase II
Anamet Phase II of three buildings-Finished Phase II Completed: Demolition of three remaining buildings and smokestack Highbay Building abated. Removal of PCB Windows Phase II
698 South Main Street-Anament New Roof The City invested $2.3M on a $3M bond commitment towards the replacement of the roof on the High Bay
Wendell Cross School – After History: A new Pre-K through 8th grade school was built in the East end of Waterbury. Demo/Construction started in the
North Main, South Main, East Main & Bank Street- After This phase of the project will remove the bricks, pave, widen and install new sidewalks,
East Main Street Utilities East Main’s Street utility work is complete as of November 30, 2020, including the removal and disposal of unsuitable soil. The
MA Green Finished Clock The clock was re-installed April 2020. The City ensures that the clock is wound on a regular basis to keep time
Library Park- After Phase I of Library Park consists of replacing all above-ground electrical utilities and installing upgraded electric utilities underground, installing a sophisticated irrigation
Brass City Harvest Food Hub The Brass Harvest Food Hub is the only food washing plant in the state. Contracted by
Train Station Contracted with Empire Paving. Continued to work with and obtain all final approvals from the Connecticut DOT, Metro-North Rail, PanAm